C-Part-Management > shop-in-factory >Project Steps


Steps to introduce shop-in-factory

 
Within the implementation of the shop-in-factory system the following project steps are necessary:
  • Appraisal of the existing stock
  • Analysis of prices regarding market relevant structures
  • Analysis of the supplier structure
  • Analysis of the products
  • Workshops with employees
  • Briefing of the suppliers
  • Detailed analysis regarding the floorstocks

During the period of implementation, the following time-slots are common:

  • Preparatory work/analyses: ca. 6 – 8 months
  • Initiation: ca 3 – 6 months






 